MR 844 – Overhaul of Steam, Water and Gas Turbines and Turbo-Generator Sets
- Monday, December 19, 2016, 15:23
- M-Clauses
- Add a comment
- sets are to be overhauled in accordance with the manufacturers’ recommendations
These periods shall commence as from the first start of operation or last overhaul of the turbo-generator set or part thereof, irrespective of the date of commencement of this insurance cover
The Insured shall advise the Insurers of any significant change In the running behaviour of the turbo-generator set and both parties shall Jointly decide on any action to be taken.
The Insured may apply for an extension of the period between overhauls. Such extension shall be granted If in the opinion of the Insurers the risk IS not aggravated thereby
If indernnifiable damage to a machine occurs after the relevant period specified in a to d has been exceeded, the Insurers shall indemnify only for the extra costs of repair excluding the costs of dismantling, reassembly and similar costs because an overhaul has to be carried out at this stage in any case. The costs of dismantling, reassembly and similar regular overhaul-related work are to be considered costs of overhauling.
If the Insured fails to comply with the requirements of this Endorsement, the Insurers shall be free of all liability for loss of gross profit following loss or damage caused by any circumstance that could have been detected had an overhaul taken place.
About the Author
Write a Comment
Gravatars are small images that can show your personality. You can get your gravatar for free today!